High-Speed Rail in AustraliaHigh-Speed Rail in Australia High-speed rail in Australia has been under investigation since the early 1980s. Every Federal Government since this time has investigated the feasibility of constructing high speed rail, but to date nothing has ever gone beyond the detailed planning stage. The most commonly suggested route is between Australia's two largest cities, Sydney and Melbourne, which is the world's second busiest air corridor. The Australian rail speed record of 210 km/h was set by Queensland Rail's Electric Tilt Train during a trial run in 1998. This speed is just above the internationally accepted definition of high-speed rail of 200 km/h (120 mph). The maximum test speed of 193 km/h set by NSW TrainLink's XPT is approximately that, and both the Transwa WDA/WDB/WDC class and XPT are capable of 200 km/h. However, these trains, as well as the V/line VLocity and Diesel Tilt Train, operate at a high of 160 km/h in passenger service. High-Speed Rail in Australia Overview The construction of a high-speed rail link along the east coast has been the target of several investigations since the early 1980s. Air travel dominates the inter-capital travel market, and intra-rural travel is almost exclusively car-based. Rail has a significant presence in the rural / city fringe commuter market, but inter-capital rail currently has very low market share due to low speeds and infrequent service. However, travel times between the capitals by high-speed rail could be as fast as or faster than air travel – the 2013 High Speed Rail Study Phase 2 Report estimated that conventional High Speed Rail express journeys from Sydney to Melbourne would take 2 hours and 44 minutes, while those from Sydney to Brisbane would take 2 hours and 37 minutes. Various studies and recommendations have asserted that a high-speed rail service between the major eastern capital cities could be viable as an alternative to air. Although such studies have generated much interest from the private sector and captured the imagination of the general public upon their release, to date no private-sector proposal has been able to demonstrate financial viability without the need for significant government assistance. A mature high-speed rail system would be economically competitive with air and automobile travel, provide mass transit without dependence on imported oil, have a duration of travel that would compare with air travel or be quicker, and would reduce national carbon dioxide emissions. Over 12 million people live along the Sydney–Melbourne rail corridor. High-Speed Rail in Australia History 1970s–1980s The rail network has long been a target of proposals for improvement. The 1979 Premiers' Meeting proposed the electrification of the Sydney–Melbourne line to improve transit time from over 12 hours to under 10, but a senate committee found this was not justified on economic grounds. In 1981, the Institution of Engineers proposed the Bicentennial High-Speed Railway Project, which proposed to link the five capitals of south-eastern Australia (Adelaide, Melbourne, Canberra, Sydney and Brisbane) in time for the Australian Bicentenary. However, it proposed only the strengthening and partial electrification of the existing tracks, new deviations to bypass the worst sections, additional passing loops, and the purchase of new diesel-electric trains. It would offer only mild improvements on the existing travel times: Sydney to Canberra in 3 hours, and Sydney to Melbourne in 9; it cannot therefore be considered a true high-speed rail proposal. New South Wales XPT In January 1978 the Public Transport Commission invited tenders for 25 high-speed railcars similar to the Prospector railcars delivered by Comeng to the Western Australian Government Railways in 1971. The tender allowed bidders to suggest alternative types of high-speed train. Comeng submitted a tender for a train based on the British Rail designed High Speed Train which had entered service in the United Kingdom in October 1976. In August 1979, Comeng was announced as the successful bidder for an order of 100 vehicles. By the time the contract was signed in March 1980, the order was only for 10 power cars and 20 carriages, enough to form four five-carriage trains with two spare power cars. The High Speed Train design was significantly modified, with the power cars being 50 cm (19.7 in) shorter, the Paxman Valenta engine downrated from 2,250 to 2,000 bhp (1,680 to 1,490 kW), gearing lowered for a top operating speed of 160 km/h (99 mph), suspension modified to operate on inferior track, and air filters and the cooling system modified to cater for hotter and dustier Australian conditions. A different light cluster was fitted along with three high-beam spotlights mounted to the roof. The passenger trailer cars were based on a Budd design, with the British Rail Mark 3 trailers considered unsuitable. The XPT entered service in 1982. It set an Australian speed record for the time of 193 km/h (120 mph) on a test run in 1992. However, the train is not often used to its full potential, operating along winding steam-era alignments, and at times has had the top speed limited due to track condition and level crossing incidents. The XPT operates at a top speed of 160 km/h (100 mph). However, it can theoretically reach speeds of 200 km/h. XPT trains currently operate services from Central railway station in Sydney to Melbourne, Brisbane, Dubbo, Grafton and Casino. 1984 CSIRO Proposal The first true high-speed rail proposal was presented to the Hawke Government in June 1984 by the CSIRO, spearheaded by its chairman, Dr Paul Wild. The proposal was to link Melbourne, Canberra and Sydney via a coastal corridor, based on French TGV (Train à Grande Vitesse) technology. The proposal estimated construction costs at A$2.5 billion ($7.0 billion in 2013), with initial revenue of A$150 million per annum exceeding operating costs of A$50 million per annum. The proposal attracted much public and media attention, as well as some private sector capital for feasibility studies. In September 1984, the Bureau of Transport Economics found that the probable construction costs had been underestimated by A$1.5 billion, and the proposal would therefore be uneconomic. The Minister for Transport, Peter Morris, rejected the proposal. Very Fast Train (VFT) Joint Venture Later in 1984 Peter Abeles, chairman of TNT, expressed interest in Dr Wild's proposal. Two years later in September 1986, the Very Fast Train Joint Venture was established, comprising Elders IXL, Kumagai Gumi, TNT and later BHP, with Dr Wild as chairman. They proposed a 350 km/h rail link from Sydney to Canberra via Goulburn, and then on to Melbourne via the coastal route (or alternatively the inland route). A feasibility study estimated to cost A$19 million ($39.5 million in 2013) was initiated by the group in 1988. In 1989, after talks with the Queensland Government, the joint venture group also performed a preliminary analysis of a coastal link to Brisbane. In 1990 the Joint Venture released the results of the major feasibility study, simply titled VFT – Project Evaluation. It proposed an inland route between Melbourne, Sydney and Canberra, with intermediate stations at Campbelltown, Bowral, Goulburn, Yass, Wagga Wagga, Albury-Wodonga, Benalla, Seymour and Melbourne Airport. It was estimated to cost $6.6 billion ($11.9 billion in 2013) and take five years to construct, beginning in 1992. The VFT was opposed by numerous groups, notably the Australian Conservation Foundation and the Australian Democrats. Concerns centred around the environmental impact a coastal corridor would have on fragile ecosystems, noise pollution and the amount of public money that might be required. After the release of the project evaluation, negotiations continued between the Joint Venture and state and federal governments. A favourable tax regime was sought, without which it was claimed that the project would not be economically viable. Premier of South Australia John Bannon was among the vocal proponents of tax breaks for major infrastructure projects such as the VFT. In August 1991, the Hawke Cabinet rejected the proposed tax breaks after it was claimed they would have cost A$1.4 billion. Subsequently the VFT Joint Venture folded. Tilting Trains During the 1990s there were several investigations into the use of tilting trains on existing tracks. In January 1990 it was reported that the NSW government was considering upgrading the existing state railway lines to utilise tilting train technology under development by Swedish-Swiss engineering giant ASEA Brown Boveri. This was at the same time as the VFT was under investigation, and there was concern that two fast railways could end up being built, which would then both be financially unviable. The tilt train concept could potentially reach speeds of up to 200 kilometres per hour (120 mph) while using the existing tracks. After the breakup of the VFT joint venture, the NSW government continued to investigate tilt trains for a time. In 1995, CountryLink brought a Swedish Railways X 2000 trainset to New South Wales to conduct an eight-week trial on the Sydney-Canberra route. The X 2000 was pulled by a specially-modified XPT power car at all times, and had one on each end. The test highlighted the deficiencies of the existing track, with tight curvature and inadequate transitions. Speed improvements over existing times were modest, and the project was abandoned – it was a case of a "fast train on slow track". Speedrail Proposal In 1993, the Speedrail Consortium (a joint venture between Alstom and Leighton Contractors) made a proposal for a high-speed rail link between Sydney and Canberra. It was initially going to cost A$2.4 billion ($4.1 billion in 2013). After years of delays and more claims that massive government subsidies would be required, in March 1997 the Commonwealth, New South Wales and ACT governments formally invited expressions of interest; by July, six proponents had been shortlisted. In December 1997, the government received four proposals, all accompanied by the required A$100,000 deposit. The Proponents Were:
On 4 August 1998, Prime Minister John Howard announced that Speedrail was the preferred party, and gave the go ahead for the project to move into the 'proving up' stage, on the understanding that if the project proceeded, it would be at "no net cost to the taxpayer". It was predicted that construction would cost A$3.5 billion ($5.4 billion in 2013), with 15,000 new jobs created during the construction period. It was planned that the line would use the East Hills line to depart Sydney, and then follow the Hume and Federal highways into Canberra. There would be stations at Central, Campbelltown, Southern Highlands, Goulburn and Canberra Airport. Nine eight-car trainsets would be used, departing from each city at 45-minute intervals, and running at a maximum speed of 320 km/h (199 mph) to complete the journey in 81 minutes. The line was to operate under a build–own–operate model, that would allow a private company to manage the network, but would then be transferred to government after 30 years. In November 1999, Speedrail submitted a feasibility study to the government, claiming that the project satisfied all the government's requirements. However, the media still speculated that A$1 billion in government assistance or tax concessions would be required. In December 2000, the federal government terminated the proposal due to fears it would require excessive subsidies. Queensland Tilt Train In March 1993 Queensland Rail issued a tender for the construction of two electric six-carriage tilting trains. In October 1994 a contract was awarded to Walkers, Maryborough with Hitachi to supply the electrical and tilting equipment. After an extensive program, on 6 November 1998 Australia's first pair of tilting trains entered service on the Spirit of Capricorn between Brisbane and Rockhampton. With a journey time of seven hours, they shaved over two hours from the schedule operated by InterCity Express sets. In July 1999 a second daily service was introduced between Brisbane and Bundaberg. Using traction equipment based on the JR Shikoku 8000 series trains, the Tilt Train set an Australian train speed record of 210 km/h (130 mph) north of Bundaberg in May 1999, a record that still stands. This makes it Australia's only train to exceed the common definition of high-speed rail, and also makes it the fastest narrow-gauge train in the world. The maximum speed of the Tilt Train in normal service is 160km/h. In August 1999 a contract was awarded to Walkers for two diesel tilting trains to operate services from Brisbane to Cairns. In contrast to the Electric Tilt Train, the diesel Tilt Train is a push-pull locomotive based train. In October 2010 Downer Rail was awarded a contract to build a further diesel tilt train with two power cars and 12 carriages to replace locomotive hauled stock on The Sunlander. The existing two diesel sets will be overhauled and extended to 10 carriages. All work was performed in Maryborough. The first refurbished set entered service in October 2013. The third and brand new set was delivered and entered service in 2014. Howard Government (2000) In December 2000 in the wake of the termination of the Speedrail proposal, the Howard Government commissioned TMG International Pty Ltd, leading a team of specialist subconsultants, including Arup, to investigate all aspects of the design and implementation of a high-speed rail system linking Melbourne, Canberra, Sydney and Brisbane. The East Coast Very High Speed Train Scoping Study – Phase 1 was released in November 2001 and cost A$2.3 million to prepare. It dealt with high-speed rail technologies, corridor selection, operating performance and transit times, project costs, projected demand, financing, and national development impacts. Although the preliminary study did not undertake a detailed corridor analysis, it recommended the selection of an inland route between Melbourne and Sydney, and a coastal route between Sydney and Brisbane. The report concluded that although a high-speed rail system could have a place in Australia's transport future, it would require years of bipartisan political vision to realise (construction time was estimated at 10–20 years), and would most likely require significant financial investment from the government – up to 80% of construction costs. Construction cost estimates indicated a strong dependence on the chosen design speed; the construction costs for a double-track east coast high speed railway would be (2001 A$):
These numbers do not include rollingstock or the cost of setting up the operating company. The report noted that these costs could be reduced somewhat upon detailed corridor analysis (especially the lower speed options) if sections of existing rail or highway corridor could be utilised. In March 2002, the Government decided not to go ahead with phase 2 of the scoping study due to the finding that an enormous amount of public funding would be required for the massive infrastructure project. Transwa WDA/WDB/WDC Class In December 2000 Westrail awarded a contract to United Goninan, Broadmeadow for nine railcars to replace the 1971 built WAGR WCA/WCE class railcars. Seven were for The Prospector and two for the AvonLink service. The first entered service on 28 June 2004. Power is provided by Cummins engines. The new railcars are capable of 200 km/h (120 mph), but track conditions restrict their top speed to 160 km/h (99 mph). Canberra Business Council Study In April 2008 the Canberra Business Council made a submission to Infrastructure Australia, High Speed Rail for Australia: An opportunity for the 21st century. The submission Detailed:
Canberra Airport Plan In 2009, Canberra Airport proposed that it would be the most appropriate location for a Second Sydney Airport, providing a high-speed rail link was built that could reduce travel times between the cities to 50 minutes. Given the existing development within the Sydney basin, a HSR link will probably be required whatever site is chosen, yet the Canberra option save up to A$22 billion which would be needed to develop a greenfields airport site at Badgerys Creek or Wilton. In June 2012, Canberra Airport unveiled plans to build a A$140 million rail terminal at the airport if the high-speed link goes ahead. Intrastate Proposals At various times, state political parties and others have proposed schemes involving fast trains in other localities that included the potential to achieve speeds above the 200 km/h threshold. In 2004, the Government of New South Wales proposed a A$2 billion privately funded underground and above-ground train line Western FastRail that would link the Sydney CBD with Western Sydney. The concept was re-proposed in December 2006 by then federal Opposition Leader Kevin Rudd during a visit to Penrith, as part of the Australian Labor Party's election platform. The plan received approving comments by the NSW State Government. The line was also backed by a consortium led by union leader Michael Easson, which includes Dutch bank ABN AMRO and Australian construction company Leighton Contractors. Elements of the proposal were incorporated into the Government's West Metro and CBD Relief Line projects. However, these plans were abandoned following the election of the O'Farrell government in 2011. In 2008, Transrapid made a proposal to the Government of Victoria to build a privately funded and operated magnetic levitation (maglev) line to serve the Greater Melbourne metropolitan area. It was presented as an alternative to the Cross-City Tunnel proposed in the Eddington Transport Report, which neglected to investigate above-ground transport options. The maglev route would connect Geelong to metropolitan Melbourne's outer suburban growth corridors, Tullamarine and Avalon domestic and international terminals in under 20 minutes, continuing to Frankston, Victoria, in under 30 minutes. It would serve a population of over 4 million people, and Transrapid claimed a price of A$4 billion. However, the Victorian government dismissed the proposal in favour of the underground metropolitan network suggested by the Eddington Report. In 2010, Western Australia's Public Transport Authority completed a feasibility study into a high-speed rail link between Perth and Bunbury. The route would follow the existing narrow gauge Mandurah line to Anketell, then the Kwinana Freeway and Forrest Highway to Lake Clifton, including 140 km (87 mi) of new track. It would replace the existing Transwa Australind passenger service, the route of which is under increasing use for freight traffic. The proposed service would have a maximum speed of 160 km/h (99 mph), at which the travel time from Perth Underground to a new station in central Bunbury would be 91 minutes. The corridor would allow for future upgrade to 200 km/h (120 mph). In the lead-up to the 2010 Victorian state election, Liberal leader Ted Baillieu promised to spend A$4 million to set up a high-speed rail advocacy unit, with the goal of ensuring Melbourne hosted Australia's first high-speed trains. He expressed support for an east coast link, and extensions west of Melbourne to Geelong and Adelaide. The 2010 Infrastructure Partnerships Australia report identified Noosa-Brisbane-Gold Coast as a potentially viable high-speed rail link, and a possible precursor to a full east-coast system. The report predicted that a 350 km/h (220 mph) system would reduce travel times between Cooroy (22 km west of Noosa) and Brisbane to 31 minutes (currently 2:08 hours), capturing as much as 84% of the total commuter market. Travel time between Brisbane and the Gold Coast would be reduced to 21 minutes, capturing up to 27% of commuters. Soon after winning the 2011 NSW state election, the incoming Liberal premier Barry O'Farrell advocated high-speed rail lines to Melbourne and Brisbane instead of a second Sydney airport, saying of a new airport site in NSW: "Whether the central coast, the south-west or the western suburbs 'of Sydney', find me an area that is not going to end up causing enormous grief to people who currently live around it". High Speed Rail Study (2011–2013) Rudd/Gillard Government (2008–2013) In December 2008, the Rudd Government announced that a Very Fast Train along the Sydney–Melbourne corridor, estimated to cost A$25 billion, was the government's highest infrastructure priority. On 31 October 2010, the Government issued the terms of reference for a strategic study to inform it and the New South Wales, Victorian, Queensland and Australian Capital Territory governments about implementation of HSR on the east coast of Australia between Melbourne and Brisbane. The initiative was supported by both the Liberal opposition and the Australian Greens, the latter of which called for the study's scope to be extended to encompass Adelaide and Perth. The $20 million study was undertaken in two phases. The report of phase 1, released on 4 August 2011, identified corridors and station locations and potential patronage, and gave indicative estimates of the cost. The first phase of the study was completed in 2011, projecting a financial cost for high-speed rail of between $61 and A$108 billion, depending on the route and station combination that was selected. The Phase 1 Report Found That An HSR Corridor Between Brisbane And Melbourne Could:
The report noted that acquiring, or otherwise preserving the corridor in the short term could reduce future costs by reducing the likelihood of additional tunnels as urban areas grow and preferred corridors become unavailable. Work on phase 2 of the study started in late 2011 and culminated in the release of the High speed rail study phase 2 report on 11 April 2013. Building on the work of phase 1, it was more comprehensive in objectives and scope, and refined many of the phase 1 estimates, particularly demand and cost estimates. In 2013 the Australian government released a study on the implementation of high-speed rail on the east coast of Australia, linking Melbourne, Canberra, Sydney, and Brisbane. Some have advocated extending the network to Adelaide or as far as Perth on the west coast. The Phase 2 Report Found That:
Also released alongside the phase 2 report were 280 detailed maps showing the preferred alignment identified in the study. Melbourne–Sydney Sydney–Brisbane Sydney–Canberra Rhumb-line distance 730 km 770 km Unknown Existing rail distance 963 km (32%+) 988 km (28% +) Unknown Existing rail average speed 92 km/h 73 km/h Unknown Existing rail travel time (h:min) 10:30 13:35 4:19 Existing rail services (daily, each way) 2 1 3 Air travel time (CBD to CBD*) (h:min) 3:00 3:05 0:55 Air services (daily, each way) 118 84 Unknown High-speed rail travel time (max. 350 km/h) 2:45 4:24 1:04 NOTE: Air travel time includes travel from CBD to airport, waiting at terminal, gate-to-gate transit, and travel to destination CBD. The Major Issues Preventing The Adoption Of High-Speed Rail Include, According To Philip Laird:
Abbott/Turnbull Government (2013–Present) On 8 November 2013 the High Speed Rail Advisory Group, charged with part of the planning for a very fast train between Brisbane and Melbourne, was one of 20 government committees and councils identified to be wound up as part of the newly elected Abbott Government's initial efforts to cut costs and "ensure that the machinery of government is as efficient and as small as possible". However, the following month, former Deputy Prime Minister Warren Truss announced that the Coalition was committed to acquiring the land corridor identified by the previous government's study, and that he was personally seeking the co-operation of the premiers of Victoria, New South Wales and Queensland, and the Chief Minister of the ACT. The Labor Party indicated it would support the move. Beyond Zero Emissions Study (2014) In 2014, the low-carbon advocacy group Beyond Zero Emissions released a detailed study in response to the Rudd government's Phase 2 report. Prepared in collaboration with the German Aerospace Centre, the study used many of the same cost assumptions but proposed a modified route to minimise construction expense. Although slightly longer (1799 km compared to 1748 km), the length in tunnel was reduced by 44%, and the length on bridges by 25%. Much of the reduction came through making greater use of existing transport corridors for metropolitan access; the government study took the politically uncomplicated but extremely expensive option of simply tunnelling to the terminal stations. Project author Gerard Drew also criticised the Phase 2 Report's 45-year construction timeline, calling it "laughable". Drew also suggested that there was significant "gold plating" evident in the government report's cost estimates. BZE forecast that the high-speed railway would cost $84.3 billion and take 10 years to construct. Turnbull Government (2015-Present) When leadership of the Liberal Party changed to Malcolm Turnbull, a noted rail enthusiast, the Federal Government revived talk of high-speed rail proposals for Australia, with a focus on private-sector proposals and value-capture funding models. In March 2016 the government received an unsolicited proposal from a group called Consolidated Land and Rail Australia (CLARA), proposing a very fast railway (500 km/h class) between Sydney and Melbourne. Rather than serving existing population centres, the proposal centred on creating 8 new inland cities as commuter towns for Sydney and Melbourne, with construction of both the cities and the railway to be funded by land sales. Clara claimed to have already secured purchase options for 40% of the land required for the cities. In April 2017, Spanish rollingstock manufacturer Talgo presented an unsolicited proposal to the NSW government, in which it was proposed to utilize passively tilting diesel rollingstock, capable of speeds up to 200 km/h, to increase speeds on the Sydney-Canberra line. With minimal modifications to the existing track, Talgo claimed a travel time as low as 2-2.5hrs could be achieved. The manufacturer offered to bring a Talgo trainset to New South Wales for testing at no cost. In the May 2017 Federal Budget, the federal government announced $20 million in funding, matching that provided by state/territory or private proponents, for the development of up to 3 business cases focusing on delivering high-speed rail links between capital cities and regional Australia. Submissions will be appraised by Infrastructure Australia, with the funds to be allocated to the successful proponents. Further funding would be considered following completion of the business case(s). Speed Records The only time a train in Australia has exceeded 200 km/h was during a test run of the Electric Tilt Train. Modifications to the tracks were required to achieve the record speed of 210 km/h. An attempt was made on an XPT test run to reach 200 km/h, although the maximum speed fell slightly short at 193 km/h. The Following Is A List Of Rail Speed Records In Australia: Date Train Location Speed 30 April 1934 Creamy Kate Between Douglas Park 75 mph (120.7 km/h) and Menangle, south of Sydney 17 November 1937 Spirit of Progress Between Werribee 79.5 mph (127.9 km/h) and Laverton, Victoria 6 September 1981 XPT Between Table Top 113.7 mph (183.0 km/h) and Gerogery, southern NSW 18 September 1992 XPT Between Table Top 119.9 mph (193.0 km/h) and Yerong Creek, southern NSW 23 May 1999 QR Electric Between Meadowvale 130.4 mph (209.9 km/h) Tilt Train and Avondale, near Bundaberg, Queensland. Quick Guide to Australia Country Guides & Australia Tourism Attractions Country Guides - Days Out - Tourism Attractions - Theme Parks - Family Days Out - Tourism Guides Quick Guide to Australia Places to Visit & Australia Cultural Tourism Theatres - Museums - Art Galleries - Cathederals - Synagogues - Mosques - Temples Festivals - Concerts - Gigs - Sport Stadiums - Sport Events - Airports Zoological Gardens - Aquariums - Racing Tracks - Racing Circuits - Athletics Tracks Quick Guide to Australia Rail Guides & Australia Rail Tourism Rail Tickets - Railway Maps - Railway Tourism Advice - Rail Passes - Rail Tours - Eurostar Eurail - Interrail - Train Stations - Metro Stations - Underground Stations Railway Modelling - Railway News Train Tickets - Rail Tours - Luxury Rail Tours - Europe Rail Pass - Steam Trains - Rail Journeys HS2 - Mountain Trains - Heritage Trains - Cog Trains - High Speed Rail - Escorted Rail Tours Cable Cars - Funicular - Gondola Lifts - Tramways - Ski Lifts - Ski Pass Railway Companies of the World - Heritage Railways - Steam Trains - Luxury Rail Journeys Airport Shuttles - Night Trains - Sleeper Rail Cars - High Speed Trains - TGV - Eurostar Cog Railways - Swiss Mountain Railways - Train Journeys - Express Trains Quick Guide to World Train Companies Amtrak - Orient Express - Rovos Rail - Rocky Mountaineer - Glacier Express Jungfrau Express - Gotthard Panorama Express - Jungfrau Travel Pass- Express Trains Eurostar - British Pullman - Bernina Express - Shongololo Express - Blue Train - Danube Express Trans Siberian Express - GoldenPass Panoramic - Golden Eagle Train - Andean Explorer Swiss Travel Pass - Jacobite - El Transcantabrico - Tren Al Andus - Hiram Bingham Australia Business Centre - Australia Exhibitions Business Centre - Trade Exhibitions - Trade Shows - Trade Fairs - Trade Events Trade Exhibition Staff - Trade Exhibition Stands - Trade Show Help Australia Business Centre - Australia Procurements Business Incorporation - Procurements - Business Leads - Foreign Exchange Business Insurance - Shares - Commodities - Futures - Property Sales - Money Transfer Asset Finance - Asset Leasing - Crowd Funding - Currency Transfer Australia Business Centre - Australia Freight Rail Freight - Rail Cargo - Multimodal Freight - Road Freight - Air Freight - Sea Freight Freight - Cargo - Containers - Pallet Delivery - Letter Delivery - Parcel Delivery Australia Business Centre - Australia Finance Business Finance - Business Insurance - Business Cards - Apprentices - Need Staff - Jobs Vehicle Finance - Car Insurance - Car Leasing - Commercial Property - Foreign Exchange Utility Swop - Utility Gas - Utility Electricity - Utility Oil - Utility Solar Power Rail Finance - Business Leasing - Crowd Funding - Currency Transfer Insurance - Utilities - Savings - Credit Cards - Car Insurances - Car Finance - Pensions Quick Guide to World Travel & Australia Tourism Hotels - Hostels - Flights - Car Rental - Flight + Hotel - River Cruises - Cruises B&B - Holiday Homes - Apartment Rentals - Chalet Rental Summer Holidays - Holiday Deals - Beach Holidays - Short Trips - Package Holidays Summer Vacations - Vacation Deals - Beach Vacations - Weekend Breaks - Package Vacations Winter Holidays - Winter Holiday Deals - Ski Holidays - Ski Lift Passes - Short Breaks Winter Vacations - Winter Vacation Deals - Ski Vacations - Ski Pass - Weekend Trips | |||||
|